Handelux
Free quote

Your solar project, step by step

Clear, transparent and handled by one team from start to finish.

  1. 1

    Contact and roof analysis

    Form or call +352 621 818 192. We check your roof on the Geoportail solar cadastre and your consumption on your bill.

    Day 1
  2. 2

    Technical visit and drone photos

    An electrician measures the roof, inspects the meter, the board and the inverter location. Drone photos feed the design.

    Week 1
  3. 3

    Detailed offer and simulation

    SolarEdge Designer layout, production simulation, Klimabonus 523/524 and communal aid calculation, net price and schedule: 30 % at signature, balance net of Klimabonus at installation.

    Week 2
  4. 4

    Contract and prefinancing mandate

    Signature of the contract and the Ministry of the Economy's 'Customer Agreement'. We file the Klimabonus prefinancing request on your behalf.

    Week 3
  5. 5

    Creos grid connection and permits

    Application on myCreos, pilot appointment, connection contracts; check of your commune's building regulations; material order.

    Weeks 3–8
  6. 6

    Installation

    Scaffolding, mounting and modules on day 1, inverter, battery, wallbox and cabling on day 2, AC connection, tests and clean-up on day 3.

    3 days
  7. 7

    Commissioning and meter

    End-of-works notification via Smarty PRO, Creos inspection, bidirectional meter, monitoring activation, handover of the acceptance report and documentation.

    Weeks 9–12
  8. 8

    Net invoice, subsidies and follow-up

    Final invoice net of Klimabonus, administrative decision for the communal application, surplus buy-back contract, and our satisfaction survey.

    Afterwards

Questions about installation and permits

Do I need a permit from the commune?

It depends on your commune's building regulations and the building's classification. In most cases a simple declaration is enough; protected buildings or sensitive zones need a permit. We check and prepare the file for you before ordering material.

What does Creos do and how long does it take?

Any installation above 800 W must be declared to the grid operator. We file the request on myCreos, Creos sets a pilot appointment and sends the connection contracts, then our electrician notifies the end of works via Smarty PRO. Creos inspects and installs the bidirectional meter within 30 days of approval. Allow 6 to 12 weeks in total depending on the season.

How long does the installation itself take?

Usually 3 working days for a house: mounting and modules, then inverter, battery and cabling, then connection, tests and clean-up. You keep your electricity during the works except for a short cut for the connection at the board.

Ready to produce your own electricity?

Free, no-obligation site visit and personalised offer within a few days.